|

BMT Home
Contact Us
Faqs
Construction Alerts
Contractors
Contracting Opportunities
Impact Schedule
Photo Gallery
LBCC Home

District Wide Projects
Pacific Coast Campus
Liberal Arts Campus

Master Plan
COC
Annual Community
Newsletter
Schedule
Program Overview
Newsletter
Glossary
Acronyms

|
The Glossary of Terms
listed below shall offer clarity to all aspects of Construction, ranging from
Pre-Award, Design, Bidding, Construction to Project Close-out. The Glossary
shall function as a quick reference sheet for commonly used terms within the
Program. This Project Glossary is a work in progress. If during the Program
other terms are encountered please submit said term to the BMT for incorporation
to the Project Glossary of Terms.
|
A
Addendum
|
|
|
A supplement
to documents, issued prior to taking receipt of bids, for the purpose of
clarifying, correcting, or otherwise changing bid documents previously
issued. |
|
Additional
Services |
|
|
Services
provided in addition to those specifically designated as basic services in
the agreement between the owner and consultant. Also known as Supplemental
Services. |
|
Agency
|
|
|
A legal
relationship by which one party is empowered and obligated to act on
behalf of another party. |
|
Agency CM
|
|
|
A form of
Construction Management performed in a defined relationship between the CM
and owner. The agency form of Construction Management establishes a
specific role of the CM acting as the Owner's principal agent in
connection with the Project. |
|
Agreement
|
|
|
A document
setting forth the relationships and obligations between two parties, as
the CM and owner or contractor and owner. It may incorporate other
documents by reference. |
|
Apparent Low
Bidder |
|
|
The bidder who
has submitted the lowest bid for a division of work described in bid
documents, a proposal form, or proposed contract. |
|
Approved
Bidders List |
|
|
The list of
contractors that have been pre-qualified for the purpose of submitting
responsible, competitive bids. |
|
Approved
Changes |
|
|
Changes in the
contract documents that have been subjected to an agreed upon change
approval process and have been approved by the party empowered to approve
such changes.
See Also:
Change Order
|
|
As-Built
Drawings |
|
|
Drawings
(plans) that show the work, as actually installed. Also known as Record
Drawings. |
|
At-Risk CM
|
|
|
A delivery
method which entails a commitment by the construction manager to deliver
the project within a Guaranteed Maximum Price (GMP). The construction
manager acts as consultant to the owner in the development and design
phases, but as the equivalent of a general contractor during the
construction phase. When a construction manager is bound to a GMP, the
most fundamental character of the relationship is changed. In addition to
acting in the owner's interest, the construction manager also protects
him/herself. |
|
B
|
|
Basic
Services |
|
|
Scope of
service as defined in the original agreement between owner and CM as basic
services. |
|
Beneficial
Occupancy |
|
|
The use of the
constructed facility by the owner prior to final completion of the
construction. |
|
Bid
|
|
|
An offer to
perform the work described in contract documents at a specified cost. |
|
Bid Bond
|
|
|
A pledge from
a surety to pay the bond amount to the owner in the event the Bidder
defaults on its commitment to enter into a contract to perform the Work
described in the Bid Documents for the bid price |
|
Bid Documents
|
|
|
The documents
issued to the contractor(s) by the owner which describe the proposed Work
and contract terms. Bid documents typically include: drawings,
specifications, contract forms, general and supplementary general
conditions, proposal or bid forms, and other information. |
|
Biddability
|
|
|
The degree to
which a set of Bid Documents could be reasonably expected to permit a
bidder to establish a competitive price to perform the Work as defined in
the Bid Documents. |
|
Biddability
Review |
|
|
A formal
review of the contract documents, addendum, and reference documents to
eliminate ambiguities, errors, omissions, and contradictions, to be
accomplished with respect to the local construction marketplace and the
bid packaging strategy; for the purpose of minimizing bid prices in the
procurement phase and disputes during construction. |
|
Bond
|
|
|
A pledge from
a surety to pay the bond amount to the Obligee (owner or contractor) in
the event of a default, or non-payment by a principal (contractor or
subcontractor), as with Bid, Performance and Labor and Material Bonds. |
|
Bonus
|
|
|
Additional
compensation paid or to be paid to a contractor by the owner as a reward
for accomplishing predetermined objectives that are over and above the
basic requirements of the contract between the owner and contractor. |
|
Budget
|
|
|
The dollar and
time amount allocated by the owner for a project. |
|
Budget
Estimate |
|
|
An estimate of
the cost of work based on preliminary information, with a qualified degree
of accuracy. |
|
C
|
|
Change Order
|
|
|
A written
agreement or directive between contracted parties which represents an
addition, deletion, or revision to the contract documents, identifies the
change in price and time and describes the nature (scope) of the work
involved. Also known as Contract Modifications.
See Also:
Contract
Modifications
|
|
Changed
Conditions |
|
|
Conditions or
circumstances, physical or otherwise, which alter the conditions or
circumstances on which the contract documents were based. |
|
Claim
|
|
|
A formal
demand for compensation, filed by a contractor or the owner with the other
party, in accordance with provisions of the contract documents. |
|
CM Fee
|
|
|
A form of
contractual payment for services, where the CM is paid a fee for services
performed. |
|
Code of
Accounts |
|
|
The owner's
written description of the cost elements of the project, used for the
owner's accounting purposes. |
|
|
|
|
Commissioning
|
|
|
Start up,
calibration, and certification of a facility. |
|
Constructibility |
|
|
The ease, with
which a project can be built, based upon the clarity, consistency, and
completeness of the contract documents for bidding, administration, and
interpretation to achieve overall project objectives. |
|
Constructibility Reviews |
|
|
The process of
evaluating the construction documents for clarity, consistency,
completeness, and ease of construction to achieve overall project
objectives. |
|
Construction
Budget |
|
|
The sum
established, normally during the planning or design phase, as available
for construction of the project. |
|
Construction
Cost |
|
|
All costs
attributed to the construction of the project, including the cost of
contracts with the contractor(s), construction support items, general
condition items; all purchased labor, material and fixed equipment.
See Also:
Cost of
Construction
|
|
Construction
Management |
|
|
A professional
service that applies effective management techniques to the planning,
design, and construction of a project from inception to completion for the
purpose of controlling time, cost and quality. |
|
Contingency
|
|
|
An amount of
money reserved by the owner to pay for unforeseen changes in the work. |
|
Contract
Modifications |
|
|
A written
agreement or directive between contracted parties which represents an
addition, deletion, or revision to the contract documents, identifies the
change in price and time and describes the nature (scope) of the work
involved. |
|
Critical Date
Schedule |
|
|
A schedule
representing important events along the path to project completion. All
milestones may not be equally significant. The most significant are termed
"major milestones" and usually represent the completion of a group of
activities.
See Also:
Milestone
Schedule
|
|
Critical Path
Method (CPM) |
|
|
A management
technique used to plan and control a project which combines all relevant
information into a single plan defining the sequence and duration of
operations, and depicting the interrelationship of the Work elements
required to complete the project. The critical path is defined as the
longest sequence of activities in a network which establishes the minimum
length of time for accomplishment of the end event of the project. Arrow
Diagramming Method (ADM) and Precedence Diagramming Method (PDM) are both
common techniques used in CPM scheduling. |
|
D
|
|
Deficient
Work |
|
|
Work
conforming to the plans, specifications, and applicable standards yet is
incomplete, insufficient, or lacking in workmanship. See "Non-conforming
Work." |
|
Design
Development |
|
|
The term used
on projects to describe the transition from the schematic phase to the
completion of the design development phase. During this phase ancillary
space is developed and dimensions are finalized. Outline specifications
are developed into technical specifications; sections are delineated and
elevations are defined.
See Also:
Design Phase
- Preliminary
|
|
Design Phase
- Final |
|
|
The phase of
the design process on a project when drawings and specifications are
completed for construction bid purposes. The phase is preceded by the
preliminary design phase, and followed by the bid and award phase. The
designation used by design professionals for the last part of the design
process prior to bidding. Also known as Construction or Working Drawings. |
|
|
|
|
Design Phase
- Preliminary |
|
|
The term used
on projects to describe the transition from the schematic phase to the
completion of the design development phase. During this phase ancillary
space is developed and dimensions are finalized. Outline specifications
are developed into technical specifications; sections are delineated and
elevations are defined. Also known as Design Development.
See Also:
Design
Development
|
|
Design Phase
- Schematic |
|
|
Traditionally
this is the first phase of a design professional's basic services. In the
schematic phase, the design professional ascertains the requirements of
the project and prepares schematic design studies consisting of drawings
and other documents illustrating the scale and relationships of the
project. |
|
Design
Professional |
|
|
The
professional individual or organization that performs the design and
prepares plans and specifications for the work to be performed. The
professional can be an architect, an engineer, or an organization which
combines professional services. |
|
Design-Build
|
|
|
Design-Build
is a project delivery method which combines architectural and engineering
design services with construction performance under one contract
agreement. |
|
Direct Costs
|
|
|
The field
costs directly attributed to the construction of a project, including
labor, material, equipment, subcontracts and their associated costs. |
|
Drawings
|
|
|
Graphic
representations showing the relationships, geometry and dimensions of the
elements of the work. |
|
E
|
|
Estimated
Cost to Complete |
|
|
The current
estimate of the remaining costs to be incurred on a project at a specific
point in time. |
|
Estimated
Final Cost |
|
|
The
anticipated cost of a project or project element when it is complete. The
sum of the cost to date and the estimated cost to complete. |
|
F
|
|
Fast Track
|
|
|
The process of
dividing the design of a project into phases in such a manner as to permit
construction to start before the entire design phase is complete. The
overlapping of the construction phase with the design phase. |
|
Fiduciary
|
|
|
An individual
or organization having duty, created by contract, to act primarily for the
owner's benefit in respect to the trust and confidence involved in the
duty and the scrupulous good faith and candor which it requires. |
|
Field Order
|
|
|
An order
issued at the site by the owner or CM to clarify and/or require the
contractor(s) to perform work not included in the contract documents. A
field order normally represents a minor change not involving a change in
contract price or time and may or may not be the basis of a change order. |
|
Final
Completion |
|
|
The date on
which the terms of all construction contracts have been satisfied. |
|
Float
|
|
|
Contingency
time that exists on a schedule of activities. It is measured by comparing
the early and late dates on a start and finish basis. |
|
Force Account
|
|
|
Directed work
accomplished by the contractor outside of the contract agreement.
|
|
G
|
|
General
Conditions |
|
|
A section of
general clauses in the Contract Specifications that establish how the
project is to be administered. Included are obligations such as providing
temporary work, insurance, field offices, etc. |
|
Guarantee
|
|
|
A legally
enforceable assurance by a third party of satisfactory performance,
quality or quantity of products or work during a specific period of time
stated and included in the contract in the event the product or work fails
to perform properly |
|
Guaranteed
Maximum Price Construction Management |
|
|
A contractual
form of the Construction Management system wherein the CM establishes a
maximum price for the cost of the Work based on an agreed-to scope.
|
|
H
|
|
|
|
I
|
|
|
|
J
|
|
|
|
K
|
|
|
|
L
|
|
Lien
|
|
|
A claim,
encumbrance, or charge against or an interest in property to secure
payment of a debt or performance of an obligation. |
|
Life Cycle
Cost |
|
|
Life cycle
costs include all costs incident to the planning, design, construction,
operation, maintenance and demolition of a facility, or system, for a
given life expectancy, all in terms of present value. |
|
Liquidated
Damages |
|
|
An amount of
money usually set on a per-day basis, which the contractor agrees to pay
the owner for delay in completing the Work in accordance with the contract
documents |
|
Long-Lead
Items |
|
|
The
identification given to material and equipment having an extended delivery
time and which may be considered for early procurement and purchase. Items
which would be delivered too late for timely installation if their
procurement or purchase were included as part of the procurement for the
entire contract or project. |
|
Long-Lead
Time |
|
|
The time
interval between purchase and delivery of long‑lead items. |
|
Low Bidder
|
|
|
The bidder who
has submitted the lowest bid, which is determined to be responsive and
responsible for a division of work described in a bid document, proposal
form or contract. |
|
Lump Sum Fee
|
|
|
A fixed amount
that includes the cost of overhead and profit paid, in addition to all
other direct and indirect costs of performing work. |
|
M
|
|
Master
Schedule |
|
|
An executive
level summary schedule identifying the major components of a project,
their sequence and durations. The schedule can be in the form of a
network, Milestone Schedule, or bar chart. |
|
Milestone
Schedule |
|
|
A schedule
representing important events along the path to project completion. All
milestones may not be equally significant. The most significant are termed
"major milestones" and usually represent the completion of a group of
activities. |
|
Multiple
Prime Contracts |
|
|
Separate
contractors contracting directly with the owner for specific and
designated elements of the work. |
|
N
|
|
Non-Conforming Work |
|
|
Work that does
not meet the requirements of the contract documents. |
|
Notice of
Award |
|
|
A formal
document informing an individual or organization of successfully securing
a contract. |
|
Notice to
Proceed |
|
|
A formal
document and/or point in the project's life cycle authorizing an
individual or organization to commence work under its contract. The
issuance of the notice to proceed typically marks the end of a procurement
phase. |
|
O
|
|
Owner
Construction Management |
|
|
A form of
Construction Management that does not use an independent construction
management organization as a team member. The owner performs all required
Construction Management services with in‑house staff. |
|
Owner's
Representative |
|
|
The individual
representing the owner on the project team. |
|
P
|
|
Penalty
|
|
|
A punitive
measure usually associated with failure to fulfill a contractual
obligation. |
|
Performance
Bond |
|
|
A pledge from
a surety to pay the bond amount to the Obligee (owner or contractor) in
the event of a default in performance of contractual obligations. |
|
Phased
Construction |
|
|
An incremental
approach to construction or design and construction. Each overlapping or
sequential phase or element to have a defined work scope and to be
considered as a separate project. |
|
Plans
|
|
|
Also known as
"Drawings".
See Also:
Drawings
|
|
Post-Construction Phase |
|
|
The period
following substantial completion. |
|
Pre-Design
Phase |
|
|
The period
before schematic design commences, during which the project is initiated
and the program is developed; the planning and conceptual phase. |
|
|
|
|
Prime
Contract |
|
|
A direct
contract with an owner. It can be a single contract and/or include the
work specified for several contracts depending upon division of work. |
|
Prime
Contractor |
|
|
A contractor
who has a contract with an owner. |
|
Professional
Services |
|
|
Services
provided by a professional or by an organization that has specific
competence in a field of endeavor that requires professional (and
technical) knowledge and capabilities and that meets recognized standards
of performance. |
|
Program
Management |
|
|
The practice
of professional construction management applied to a capital improvement
program of one or more projects from inception to completion.
Comprehensive construction management services are used to integrate the
different facets of the construction process - planning, design,
procurement, construction and activation - for the purpose of providing
standardized technical and management expertise on each project.
See Also:
Construction
Management
|
|
Progress
Meeting |
|
|
A meeting
dedicated to the subject of progress during any phase of project delivery.
|
|
Progress
Payment |
|
|
Partial
payment of the contract amount periodically paid by the owner, upon
approval by the CM, verifying that portions of the Work have been
accomplished. |
|
Project
|
|
|
The total
effort required in all phases from conception through design and
construction completion to accomplish the owner's objectives. |
|
Project
Budget |
|
|
The sum or
target figure established to cover all the owner's costs of the project.
It includes the cost of construction and all other costs such as land,
legal and professional fees, interest, and other project‑related costs. |
|
Project Cost
|
|
|
The actual
cost of the entire project. |
|
Project
Management |
|
|
The use of
integrated systems and procedures by a team of professionals during
project design and construction. As applied to a construction project,
Project Management can be used synonymously with Construction Management. |
|
Project
Procedures Manual |
|
|
A detailed
definition of the project team responsibilities and authority, project
systems, and procedures. |
|
Project Team
|
|
|
Initially
consists of the owner, design professional, and CM. Thereafter, as prime
construction contractors are engaged they are added to the Team. |
|
Project Team
Meeting |
|
|
A meeting
dedicated to all aspects of the project, involving the project team
members (owner, design professional, CM, contractor(s)). |
|
Punch List
|
|
|
A list made
near the completion of the construction work indicating items of work that
remain unfinished, do not meet quality or quantity requirements as
specified or are yet to be performed by the contractor prior to completing
the terms of the contract. |
|
Q
|
|
Quality
|
|
|
The degree to
which the project and its components meet the owner's expectations,
objectives, standards, and intended purpose; determined by measuring
conformity of the project to the plans, specifications, and applicable
standards. |
|
Quality
Assurance (QA) |
|
|
The
application of planned and systematic methods to verify that quality
control procedures are being effectively implemented. |
|
Quality
Control (QC) |
|
|
The continuous
review, certification, inspection, and testing of project components,
including persons, systems, materials, documents, techniques, and
workmanship to determine whether or not such components conform to the
plans, specifications, and applicable standards. |
|
Quality
Management |
|
|
The process of
planning, organization, implementation, monitoring and documenting of a
system of policies and procedures that coordinate and direct relevant
project resources and activities in a manner that will achieve quality.
See Also:
Quality
|
|
R
|
|
Record
Drawings |
|
|
Drawings
(plans), prepared after construction is complete that represent the work,
accomplished under the contract. |
|
Recovery
Schedule |
|
|
The schedule
that depicts action(s) and special effort(s) required to recover lost time
in the original Master Schedule. It can depict activities of any member of
the project Team. |
|
Request for
Change Proposal |
|
|
A delineation
and/or narrative issued by the CM to the contractor that describes a
proposed change to the contract documents for purposes of establishing
cost and time impacts. May also be known as Bulletin, Request for
Information, and Request for Quote. |
|
S
|
|
Schedule of
Values |
|
|
A list of
basic contract segments in both labor and material, where each line item
consists of a description of a portion of work and a related cost and the
sum of the lines of the contract equals the total contract price.
Generally used to determine progress payments to contractor(s). |
|
Scope
|
|
|
Identification
of all requirements of a project or contract. |
|
Scope Changes
|
|
|
Changes that
expand or reduce the requirements of the project during design or
construction. |
|
Shop Drawings
|
|
|
| | |